News

Nuclear Reactors' Cost: $17 Billion

Mar 11, 2008 (The News & Observer)

[Editor's note:  As the note following this article indicates, the cost of electricity from these reactors---should the ever be built---could be $0.25cents/kwh, which is five times the general estimate for wind power today.  For anyone bothering to do the math, it is hard to imagine a long-term power production investment as nonsensical as nuclear power.]

Building two nuclear reactors in Florida would cost Progress Energy $17 billion, which would increase the bills of the company's customers in that state by an average of 3 percent to 4 percent a year for 10 years.

The cost estimates, to be filed with Florida regulators today, are an early indication of Progress' potential nuclear costs in North Carolina. The utility, based in Raleigh, is considering two new reactors at its Shearon Harris site in Wake County. The reactors proposed in Florida -- the Westinghouse AP1000 -- are the same models that Progress is planning at Shearon Harris.

The costs of building multibillion-dollar power plants are paid by utility customers through their monthly bills over several decades. Such costs have been shrouded in speculation as utilities, vendors and manufacturers sought to promote a resurgence in nuclear power while avoiding the negative repercussions of sticker shock.

Today's filing before the Florida Public Service Commission will be the subject of hearings in that state this year about the need for nuclear plants. It's one of the nation's first cost estimates for new reactors and is consistent with a recent appraisal from Florida Power & Light for two
Westinghouse units.

Progress officials promote nuclear energy as the cheapest option for meeting growing energy demand. Several years ago, the company was projecting a cost of $2 billion to $3 billion per reactor, but since then the cost of labor and materials has skyrocketed amid increasing global demand for energy.

Nuclear energy had stalled after the 1979 accident at Three Mile Island in Pennsylvania, but the technology has gained new advocates because of concerns about global warming.

The operation of nuclear generators, unlike that of coal-burning power plants, does not produce carbon dioxide, the greenhouse gas blamed for heating the planet. Supporters promote nuclear energy as a clean fuel, despite its lethal byproduct: radioactive nuclear waste.

Nuclear critics who advocate renewable energy and conservation programs are sure to seize on the newest estimates as evidence that nuclear costs are spiraling out of control.

During the last period of nuclear expansion three decades ago, critics say, utilities lowballed nuclear cost estimates only to revise them mid-construction. In the 1970s, for example, the construction of Shearon Harris was originally projected to cost $1.1 billion for four reactors, but the actual cost was $3.9 billion for one reactor. The other three reactors were canceled amid cost overruns and reduced demand forecasts.

Progress is expected to submit a more detailed cost estimate for the Florida nuclear plants in May. The company's nuclear cost estimates include financing, land acquisition, construction, labor and regulatory fees. Progress spokesman Rick Kimble warned against extrapolating costs in North Carolina from the Florida estimates. He noted that the utility has not signed a contract with Westinghouse for reactors for North Carolina and could continue negotiating for months.

Progress officials have said they would not reveal cost estimates for new reactors at Shearon Harris until the company negotiates a contract. Progress' Florida cost estimate includes $3 billion to build about 200 miles of transmission lines and substations in 10 counties, an expense not anticipated in North Carolina.

In this state, the new reactors would be placed at a site that was designed for four reactors. The Florida nuclear plants, however, would be built about seven miles from the company's Crystal River Nuclear Plant on 3,100 acres of former timberland that Progress bought for about $43 million last year.

The first of Progress' planned nuclear plants in Florida is expected to begin operation in 2016, with the second unit going online in 2017. In North Carolina, the first unit would begin operating between 2018 and 2020 if the company decides it can afford to build it. A final decision is at least a year away.

EDITORS NOTE: If one 1100-mW nuclear plant and infrastructure costs $8.5 billion, then the installed capacity cost is $7,727/kW. If such a plant operated with a 90% capacity factor and 20% of the gross generation was lost to meet the needs for the parasitic requirements of the facility's internal pumps and such, and said facility was financed at a 9% interest rate for a 30 year period, then the amortization would result in a cost of about 12.0 cents/kWh. Adding to that the roughly 2.0 cents/kWh needed for the production costs means the busbar power cost is about 14.0 cents/kWh. Accounting for the non-factored costs of transmission and distribution will be a roughly 2x multiple of the busbar cost, meaning that the delivered cost to the end consumer is roughly 25.0 cents/kWh. By logic, any conservation, efficiency or renewable technology placed on the customer's side of the meter that costs less than 25.0 cents/kWh should be deployed first, as they will be more "cost-effective" than buying the electron of nuclear generation. While the use of the Shearson Harris site in NC will provide some common infrastructure, there will be a cost for adding the required upgrade to transmission lines and substations. Even if no infrastructure upgrades were required, the busbar cost at Harris would still be about 12.0 cents/kWh.

This cost calculation was written by Phil Lusk.